Renovation runs from messy and hidden work to clean and visible work. Getting the order wrong usually means paying to redo something. This is the usual sequence; your subcontractors may adjust it for your home.
- Hacking and demolition. Remove what is going before anything new is ordered.
- Plumbing and electrical, first stage. Pipes and wiring are run while walls and floors are still open.
- Masonry and tiling. Screed, waterproof wet areas, then lay tiles.
- Air-conditioning piping and trunking, before ceilings and carpentry hide it.
- False ceiling and partitions.
- Carpentry. Measured on site after tiling, then built and installed.
- Painting, with touch-ups at the end.
- Shower screens and mirrors, measured after bathroom tiling is complete.
- Fixtures and appliances: lights, fans, sanitary ware, switches and sockets.
- Curtains and blinds, measured after painting.
- Cleaning and final touch-ups, then your defects check.
Three things that catch people out
- Carpentry is made off site and takes weeks. Confirm it early so it is ready when the site is.
- Order long-lead materials (tiles, countertops, doors) before the trade that needs them is due.
- Decide appliance models before carpentry is measured. Cabinets are built around them.
When you start a renovation on My Direct Reno, your dashboard lists the trades for your type of renovation in this order.
General information only, not professional advice.